Masjid Touba Project

The Murid Islamic Community in America (MICA) is currently carrying out reconstruction work. Details of the reconstruction can be found below:

Masjid Touba Reconstruction Basic Work / Services
1) Architect Building Code Review: August 2012
2) Reconstruction Program: August 2012 – January 2013
3) Architect Contract Review & Signature: January 2013 – May 2013
4) Schematic Design Phase: May 2013 – October 2013
5) Design Development Phase: October 2013 – December 2013
6) Application Filled w/ DOB: December 20, 2013
7) Construction Documents Phase: In Progress
8) Bidding or Negotiation Phase: TBD
9) Construction Phase: TBD
10) Closeout / Expedite Final C of O: TBD

To view pictures of the project, please view the link here. Additional project details are listed below:

  1. Corporation Opinion Letter
  2. HPD Certification Letter
  3. Notice of Objections, 15th April, 2015
  4. 2014 Property Tax Exemption
  5. HPD Registration
  6. 46 Edgecombe Avenue Deed
  7. HPD Application Certificate of No Harassment
  8. HPD Application Certificate of No Harassment – Amendment
  9. 2015-2018 Certificate of No Harassment
  10. MICA Certificate Under Seal
  11. Up to Date Project Costs
  12. GC Signed Contract – A
  13. Minutes of the Construction Technical Meeting – 1
  14. Application for Payment – 2